Ike Damage Status Report

11/21/2008

Clear Creek Independent School District

Status of Hurricane Ike – Two Months After the Storm

As of 11/21/2008

 

Completed

Damage caused by rising water at 2 campuses and falling water (caused by damaged roofs) at more than 40 campuses and facilities has been assessed and protective measures have been taken to remove contaminates (water, mold, debris, etc.) at a cost of more than $3.4 million.

 

Approximately 8,250 cubic yards of debris has been removed from over 40 campuses at a cost of more than $1.5 million.

 

Damaged kitchen equipment at one campus has been replaced and the kitchen has re-opened at a cost of more than $200,000.

 

Food and kitchen supplies damaged by water and the loss of power at district facilities have been replaced at a cost of more than $105,000.

 

Roof assessments have been completed at all district facilities and temporary repairs have been made at over 25 locations at a cost of more than $450,000.

 

HVAC repairs and replacements at more than 10 campuses have been completed at a cost of more than $307,250.

 

 

In progress

Carpet and Vinyl flooring is currently being installed at over 20 campuses at an estimated cost of $815,000.

 

Wood floors (gyms, dance floors, etc.) are currently being installed and repaired at more than 15 campuses at an estimated cost of $1,024,000.

 

Roof replacements at the first 7 campuses are under way and scheduled to be substantially complete by the first week of December (weather permitting) at a cost of $3.6 million.

 

Fencing projects at two district high school baseball fields are in progress at an estimated cost of $120,000.

 

Technology repairs and replacements (computers, printers, telephones, etc.) totaling more than $480,000 are under way and scheduled to be completed by January 2009.

 

Future needs

Roof replacement contracts at the remaining 7 campuses are scheduled to be awarded in December, with work beginning in late December, and estimated completion in April 2009.  The estimated cost for these 7 campuses is more than 3 million.

 

Numerous other categories of damages totaling more than $3.2 million have been assessed and estimated.  The bid and quote process is under way to obtain favorable pricing and comply with state purchasing laws.

 

 

ljeffcoa

Facebook DZone It! Digg It! StumbleUpon Technorati Del.icio.us NewsVine Reddit Blinklist Furl it!

Education Support Center
2425 E. Main Street
League City, Texas 77573
(281) 284-0000

Directions to the ESC   |   Site Disclaimer
© Copyright 2009. All Rights Reserved.

*Some sections of this site require: Adobe® READER®, Adobe® FLASH® player and iTunes®.
Site Optimized for Internet Explorer; 1024 x 768 Display Setting.

Download Adobe Acrobat Reader Download Adobe Flash PlayerDownload iTunes